DECISION MAKING TECHNIQUES: RELEVANT COST ANALYSIS – COMPLETE GUIDE WITH EXAMPLES AND CALCULATIONS

Introduction

Every business decision involves a choice between alternatives. Should we make or buy this component? Should we accept this special order at a discount? Should we discontinue this product line? Should we replace this equipment?

The key to making good decisions is focusing on the costs and revenues that actually differ between the alternatives—and ignoring those that do not. This is the essence of relevant cost analysis.

Relevant costing is a decision-making technique that identifies the costs and revenues that are relevant to a specific decision. It recognises that not all costs are relevant to every decision. Some costs are sunk—already incurred and unrecoverable. Some costs are unavoidable—they will be incurred regardless of the decision. Some costs are allocated—they are arbitrarily spread across products or departments. None of these are relevant to the decision at hand.

For Nigerian businesses, operating in an environment of constrained resources and volatile costs, the ability to distinguish relevant from irrelevant costs is essential. A wrong decision—based on distorted cost information—can destroy value. A right decision—based on relevant costing—can create it.

At Qeeva Advisory, we understand that relevant cost analysis is not just an academic exercise—it is a practical tool for making better decisions. Our team helps Nigerian businesses apply relevant costing to pricing, product mix, outsourcing, and investment decisions.

This comprehensive guide examines decision-making techniques using relevant cost analysis, covering the key concepts, the types of costs that matter, and worked examples with calculations.

Close-up of hands using a calculator next to a company invoice, depicting a financial calculation concept.

The Pain Points: Why Cost Analysis Goes Wrong

The Full Cost Fallacy

Many businesses make decisions using full absorption cost—the total cost including allocated fixed overheads. This can lead to wrong decisions. A product that appears unprofitable on a full cost basis may be profitable on a relevant cost basis, because the allocated overhead would not disappear if the product were discontinued.

The Sunk Cost Trap

Sunk costs are costs that have already been incurred and cannot be recovered. They are irrelevant to future decisions. Yet many decision-makers continue to consider sunk costs—”we’ve already spent so much on this project, we can’t stop now”—leading to escalation of commitment to failing ventures.

The Opportunity Cost Blind Spot

Opportunity cost is the value of the foregone alternative—what you give up by choosing one option over another. It does not appear in the accounting records, but it is a real cost of the decision. Ignoring it leads to decisions that look profitable but are not.

Understanding Relevant Costs

What Makes a Cost Relevant?

A cost is relevant to a decision if it meets two criteria:

It must be a future cost – Costs already incurred (sunk costs) are not relevant.

It must differ between alternatives – Costs that are the same under all alternatives are not relevant.

Types of Costs and Their Relevance

Cost Type Definition Relevant?
Sunk Cost Already incurred, cannot be recovered No
Committed Cost Will be incurred regardless of decision No
Allocated Fixed Cost Arbitrarily spread across products/departments Usually No
Avoidable Cost Will be avoided if a particular decision is taken Yes
Incremental Cost Additional cost incurred by taking a decision Yes
Opportunity Cost Value of the foregone alternative Yes
Relevant Cost Future, differential cash flow Yes

Sunk Costs

Sunk costs are costs that have already been incurred and cannot be recovered, regardless of the decision made. Examples include:

  • Research and development costs already spent

  • Equipment purchased for a project that is now being reconsidered

  • Market research already conducted

Key principle: Sunk costs are irrelevant to future decisions. The money is already spent. The only question is: what should we do now?

Committed Costs

Committed costs are costs that will be incurred regardless of the decision. They are unavoidable. Examples include:

  • Rent on a building under a non-cancellable lease

  • Salaries of permanent staff who cannot be made redundant

  • Depreciation on assets already owned (where no disposal is contemplated)

Key principle: Committed costs are not relevant because they do not differ between alternatives.

Allocated Fixed Costs

Allocated fixed costs are overheads that are spread across products or departments using an arbitrary basis (e.g., floor space, labour hours). They are not caused by any specific product—they would be incurred even if the product were discontinued.

Key principle: Allocated fixed costs are generally not relevant to product-level decisions, because they do not change with the decision.

Avoidable Costs

Avoidable costs are costs that will be avoided if a particular decision is taken. Examples include:

  • Materials that will not be purchased if a product is discontinued

  • Labour that can be made redundant if a department is closed

  • Variable overheads that vary with production

Key principle: Avoidable costs are relevant because they differ between alternatives.

Incremental Costs

Incremental costs are the additional costs incurred by taking a decision. They are relevant.

Key principle: If a decision increases costs, the increase is relevant. If it decreases costs, the decrease is relevant.

Opportunity Costs

Opportunity cost is the value of the benefit foregone by choosing one alternative over another. It does not appear in the accounting records, but it is a real cost of the decision.

Key principle: Opportunity costs are relevant because they differ between alternatives.

Worked Example 1: Special Order Decision

The Scenario

A Nigerian manufacturer produces a product with the following costs per unit:

Cost Item Amount (₦)
Direct materials 2,000
Direct labour 1,500
Variable overhead 500
Fixed overhead (allocated) 1,000
Full cost 5,000

Normal selling price: ₦6,000 per unit.

The company receives a special order from a new customer for 1,000 units at ₦4,500 per unit. The customer is in a different market and will not affect normal sales. The company has spare capacity.

Question: Should the special order be accepted?

Analysis

Step 1: Identify relevant costs

The fixed overhead of ₦1,000 per unit is allocated—it will be incurred regardless of whether the special order is accepted. It is not relevant.

The relevant costs are the variable costs:

Relevant Cost Amount (₦ per unit)
Direct materials 2,000
Direct labour 1,500
Variable overhead 500
Total relevant cost 4,000

Step 2: Compare relevant cost with the offer price

Item Amount (₦ per unit)
Offer price 4,500
Relevant cost 4,000
Contribution per unit 500

Step 3: Calculate total contribution

  • 1,000 units × ₦500 = ₦500,000

Conclusion: The special order should be accepted. It contributes ₦500,000 toward fixed costs and profit. The full cost of ₦5,000 is irrelevant because the fixed overhead would be incurred regardless.

The Trap

If the company used full cost, it would see a loss of ₦500 per unit (₦4,500 − ₦5,000) and reject the order. But that would be wrong—the full cost includes an allocated fixed overhead that does not change with the decision.

Professional setting with people handling cash and calculations using a calculator at a desk.

Worked Example 2: Make or Buy Decision

The Scenario

A Nigerian company currently manufactures a component used in its main product. The costs for 10,000 units are:

Cost Item Amount (₦)
Direct materials 5,000,000
Direct labour 3,000,000
Variable overhead 1,000,000
Fixed overhead (allocated) 2,000,000
Total cost 11,000,000
Cost per unit 1,100

An external supplier offers to supply the component for ₦950 per unit. If the company buys externally, the manufacturing facilities currently used could be rented out for ₦800,000 per year.

Of the fixed overhead, ₦1,200,000 is directly attributable to the component and would be avoided if production ceases. The remaining ₦800,000 is allocated and would continue.

Question: Should the company make or buy?

Analysis

Step 1: Identify relevant costs for “make”

Relevant Cost Amount (₦)
Direct materials 5,000,000
Direct labour 3,000,000
Variable overhead 1,000,000
Avoidable fixed overhead 1,200,000
Total relevant make cost 10,200,000

Step 2: Identify relevant costs for “buy”

Relevant Cost Amount (₦)
Purchase price (10,000 × ₦950) 9,500,000
Total relevant buy cost 9,500,000

Step 3: Consider opportunity cost

If the company buys, it can rent out the facilities for ₦800,000. This is an opportunity cost of making (the benefit foregone by not renting out the facilities).

Item Make (₦) Buy (₦)
Relevant costs 10,200,000 9,500,000
Opportunity cost (rent foregone) 800,000 0
Total relevant cost 11,000,000 9,500,000

Conclusion: Buying is cheaper by ₦1,500,000. The company should buy the component.

Key Points

  • The allocated fixed overhead of ₦800,000 was excluded because it would continue regardless of the decision.

  • The avoidable fixed overhead of ₦1,200,000 was included in the make cost because it would be avoided if production ceased.

  • The opportunity cost of ₦800,000 (rent foregone) was included in the make cost because it represents a benefit given up by choosing to make.

Worked Example 3: Discontinuation Decision

The Scenario

A Nigerian company produces three products. The financial results for the year are:

Item Product A (₦) Product B (₦) Product C (₦) Total (₦)
Sales 10,000,000 8,000,000 5,000,000 23,000,000
Variable costs 6,000,000 5,500,000 4,000,000 15,500,000
Contribution 4,000,000 2,500,000 1,000,000 7,500,000
Fixed costs (allocated) 2,000,000 1,600,000 1,000,000 4,600,000
Profit/(Loss) 2,000,000 900,000 0 2,900,000

Product C shows a profit of zero. Management is considering discontinuing Product C.

Of the fixed costs allocated to Product C (₦1,000,000), ₦600,000 is avoidable if the product is discontinued. The remaining ₦400,000 is general fixed overhead that will be reallocated to other products.

Question: Should Product C be discontinued?

Analysis

Step 1: Identify relevant costs and revenues

If Product C is discontinued:

  • Contribution of ₦1,000,000 will be lost

  • Avoidable fixed costs of ₦600,000 will be saved

Step 2: Calculate the net effect

Item Amount (₦)
Contribution lost (1,000,000)
Avoidable fixed costs saved 600,000
Net loss from discontinuing (400,000)

Conclusion: Discontinuing Product C would reduce overall profit by ₦400,000. The product should not be discontinued.

Key Points

  • The allocated fixed costs of ₦1,000,000 are not relevant in full. Only the avoidable portion (₦600,000) is relevant.

  • Product C contributes ₦1,000,000 toward fixed costs and profit. Even though its profit after allocation is zero, it is still making a positive contribution.

  • Discontinuing it would lose that contribution while saving only ₦600,000 in avoidable fixed costs.

Worked Example 4: Accept or Reject with Opportunity Cost

The Scenario

A Nigerian company has a machine that is operating at full capacity. It produces two products:

Item Product X Product Y
Selling price per unit ₦10,000 ₦15,000
Variable cost per unit ₦6,000 ₦11,000
Contribution per unit ₦4,000 ₦4,000
Machine hours per unit 2 hours 4 hours

The company has 1,000 machine hours available per month.

Question: Which product should the company prioritise?

Analysis

Step 1: Calculate contribution per machine hour

Item Product X Product Y
Contribution per unit ₦4,000 ₦4,000
Machine hours per unit 2 4
Contribution per machine hour ₦2,000 ₦1,000

Step 2: Compare

Product X generates ₦2,000 per machine hour. Product Y generates ₦1,000 per machine hour.

Conclusion: The company should prioritise Product X. It generates twice the contribution per unit of the scarce resource (machine hours).

Key Point

When a resource is scarce (a limiting factor), the decision should be based on contribution per unit of the scarce resource, not contribution per unit of product. This maximises total contribution.

Close-up of a person's hand using a calculator on a desk with financial documents.

Worked Example 5: Replacement Decision

The Scenario

A Nigerian company is considering replacing an old machine with a new one.

Old Machine:

  • Original cost: ₦10,000,000

  • Current book value: ₦4,000,000

  • Remaining useful life: 4 years

  • Resale value now: ₦1,000,000

  • Annual operating costs: ₦3,000,000

  • Annual depreciation: ₦1,000,000

New Machine:

  • Cost: ₦12,000,000

  • Useful life: 4 years

  • Resale value at end of 4 years: ₦2,000,000

  • Annual operating costs: ₦1,500,000

  • Annual depreciation: ₦2,500,000

Question: Should the company replace the machine?

Analysis

Step 1: Identify relevant costs

The original cost of ₦10,000,000 and the current book value of ₦4,000,000 are sunk costs. They are not relevant.

The relevant costs are the future cash flows:

Item Keep Old (₦) Replace with New (₦)
Resale value of old machine (now) 0 1,000,000 (inflow)
Cost of new machine 0 (12,000,000)
Operating costs (4 years) (12,000,000) (6,000,000)
Resale value of new machine (end of year 4) 0 2,000,000 (inflow)
Net relevant cost (12,000,000) (15,000,000)

Step 2: Compare

Decision Net Relevant Cost (₦)
Keep old 12,000,000
Replace 15,000,000

Conclusion: Keeping the old machine is cheaper by ₦3,000,000. The company should not replace the machine.

Key Points

  • The original cost and book value of the old machine are sunk costs—they are irrelevant.

  • Depreciation is not a cash flow and is not relevant (except for tax effects, which are ignored in this simplified example).

  • Only the future cash flows—resale values, purchase cost, and operating costs—are relevant.

Key Principles for Relevant Cost Analysis

1. Focus on Future Cash Flows

Only future cash flows are relevant. Historical costs, book values, and depreciation are not relevant.

2. Ignore Sunk Costs

Money already spent is gone. Decisions should be based on what will happen, not what has happened.

3. Include Opportunity Costs

The value of the foregone alternative is a real cost of the decision. Include it.

4. Consider Avoidable Costs

Costs that will be avoided if a decision is taken are relevant. Costs that will continue regardless are not.

5. Be Careful with Allocated Fixed Costs

Allocated fixed costs are usually not relevant because they do not change with the decision.

6. Consider Qualitative Factors

Not all relevant factors are financial. Quality, reputation, employee morale, and strategic positioning may be relevant to the decision.

Common Relevant Cost Analysis Mistakes

1. Including Sunk Costs. Sunk costs are irrelevant. Including them leads to throwing good money after bad.

2. Including Allocated Fixed Costs in Full. Allocated fixed costs are usually not relevant. Only the avoidable portion matters.

3. Ignoring Opportunity Costs. The value of the foregone alternative is a real cost. Ignoring it leads to decisions that look profitable but are not.

4. Using Full Cost Instead of Relevant Cost. Full cost includes allocated overhead that may not change with the decision. Use relevant cost instead.

5. Ignoring Qualitative Factors. Quality, reputation, and employee morale matter. A decision that looks good on paper may be disastrous in practice.

6. Failing to Consider the Limiting Factor. When resources are scarce, decisions should be based on contribution per unit of the scarce resource.

How Qeeva Advisory Helps with Relevant Cost Analysis

At Qeeva Advisory, we understand that relevant cost analysis is not just an academic exercise—it is a practical tool for making better decisions. Our team helps Nigerian businesses apply relevant costing to pricing, product mix, outsourcing, and investment decisions.

Our Core Services

Decision Making Techniques: Relevant Cost Analysis – Our comprehensive guide to relevant costing, with worked examples and calculations.

Cost Accounting & Cost Management Service – We provide specialised cost accounting and cost management services, using proven methodologies including relevant costing.

Cost Volume Profit Analysis – Complete guide to CVP, break-even, contribution margin, and decision making.

Make or Buy Decisions – Complete guide to relevant costing, special orders, and outsourcing.

Standard Costing Guide – Setting standards, variance analysis, and performance management.

Activity Based Costing – Complete guide to ABC cost drivers and implementation.

Advisory Services Nigeria – Our advisory professionals provide guidance on cost management and decision-making.

Our Relevant Cost Methodology

Phase 1: Decision Definition – We help you define the decision and identify the alternatives. Clear definition prevents scope creep and ensures analysis is focused.

Phase 2: Cost Identification – We identify all costs associated with each alternative. We classify them as relevant or irrelevant.

Phase 3: Analysis and Calculation – We calculate the relevant costs for each alternative, considering opportunity costs where appropriate.

Phase 4: Qualitative Assessment – We consider qualitative factors that may affect the decision.

Phase 5: Recommendation – We present findings and provide a recommendation, with clear reasoning.

Frequently Asked Questions

Q: What is relevant cost analysis?

A: Relevant cost analysis is a decision-making technique that identifies the costs and revenues that differ between alternatives, focusing on future cash flows and ignoring sunk costs.

Q: What are sunk costs?

A: Sunk costs are costs that have already been incurred and cannot be recovered. They are irrelevant to future decisions.

Q: What is opportunity cost?

A: Opportunity cost is the value of the benefit foregone by choosing one alternative over another. It is a real cost of the decision, even though it does not appear in the accounting records.

Q: What is the difference between avoidable and unavoidable costs?

A: Avoidable costs will be avoided if a particular decision is taken. Unavoidable costs will be incurred regardless. Only avoidable costs are relevant.

Q: How do I calculate the relevant cost for a make-or-buy decision?

A: Compare the relevant costs of making (variable costs plus avoidable fixed costs plus opportunity costs) with the relevant costs of buying (purchase price plus any additional costs).

Q: What is the key principle in a special order decision?

A: The order should be accepted if the offer price exceeds the relevant (variable) cost, provided there is spare capacity and the order does not affect normal sales.

Q: How can Qeeva Advisory help with relevant cost analysis?

A: We help you define decisions, identify relevant costs, perform the analysis, and make recommendations. Our services help you make better decisions with confidence.

Analyze financial trends using charts, calculator, and data tools.

The Bottom Line

Relevant cost analysis is a powerful tool for decision making. It focuses attention on the costs and revenues that matter—those that differ between alternatives—and ignores those that do not. By understanding sunk costs, opportunity costs, and the distinction between avoidable and unavoidable costs, businesses can make better decisions.

For Nigerian businesses, operating in an environment of constrained resources and volatile costs, the ability to apply relevant costing is essential. A wrong decision—based on distorted cost information—can destroy value. A right decision—based on relevant costing—can create it.

Key Takeaways:

Focus on Future Cash Flows – Only future cash flows are relevant to decisions.

Ignore Sunk Costs – Money already spent is gone. Decisions should be based on what will happen, not what has happened.

Include Opportunity Costs – The value of the foregone alternative is a real cost.

Consider Avoidable Costs – Costs that will be avoided if a decision is taken are relevant.

Be Careful with Allocated Fixed Costs – Allocated fixed costs are usually not relevant.

Your job is to be prepared. Define your decision. Identify your relevant costs. Perform the analysis. Consider qualitative factors. Seek professional guidance.

With the right approach and the right partner, you can turn relevant cost analysis from an academic exercise into a driver of better decisions.

Suggested Reading from Our Blog

Decision Making Techniques: Relevant Cost Analysis – This comprehensive guide with worked examples and calculations.

Cost Accounting & Cost Management Service – Specialised cost accounting and cost management services.

Cost Volume Profit Analysis – Complete guide to CVP, break-even, and contribution margin.

Make or Buy Decisions – Complete guide to relevant costing, special orders, and outsourcing.

Standard Costing Guide – Standards, variance analysis, and performance management.

Activity Based Costing – ABC cost drivers and implementation.

Advisory Services Nigeria – Cost management and decision-making guidance.

Dealing with Risk and Uncertainty in Decision Making – Probability, sensitivity analysis, and risk management.

Reference Links / Sources

Qeeva Advisory – Decision Making Techniques: Relevant Cost Analysis – Relevant costing with examples and calculations.

Qeeva Advisory – Cost Accounting & Cost Management Service – Cost accounting methodologies.

Qeeva Advisory – Cost Volume Profit Analysis – CVP and decision making.

Qeeva Advisory – Make or Buy Decisions – Relevant costing and outsourcing.

Qeeva Advisory – Standard Costing Guide – Standards and variance analysis.

Qeeva Advisory – Activity Based Costing – ABC cost drivers.

Qeeva Advisory – Advisory Services Nigeria – Cost management and decision-making.

Qeeva Advisory – Dealing with Risk and Uncertainty – Risk and uncertainty in decision making.

Let’s Talk About Your Decision Making Needs

Applying relevant cost analysis to your decisions requires technical expertise and disciplined analysis. At Qeeva Advisory, we understand the challenges faced by Nigerian businesses.

Whether you need help with special order decisions, make-or-buy analysis, product discontinuation, or equipment replacement, we are here to support you.

📞 Call us: (+234) 802 320 0801, (+234) 807 576 5799

📧 Email: info@qeeva.com

📍 Visit us: 5, Ishola Bello Close, Off Iyalla Street, Alausa, Ikeja, Lagos, Nigeria

Contact us today to schedule a decision analysis consultation. Let us help you make better decisions with confidence.

Your journey to better decisions starts with a conversation. Let’s talk.

author-avatar

About Matthew Ogagavworia, FCA

Matthew Ogagavworia, FCA, is the Managing Partner of Matthew Ogagavworia & Co. (Chartered Accountants) and Matog Consulting. A Fellow Chartered Accountant with more than 25 years in practice, he advises companies, investors, NGOs and public institutions across Nigeria on audit and assurance, tax, forensic accounting, valuation, corporate restructuring and management consulting. He works from the firm's offices in Ikeja, Lagos and Warri, Delta State.